vanessaskye6414 vanessaskye6414
  • 23-05-2023
  • Business
contestada

1. Find the schedule and cost variances for a project that has an actual cost at month 22 of $540,000, a scheduled cost of $523,000, and an earned value of $535,000. Show work and provide a detailed explanation of the results.

Respuesta :

Otras preguntas

What is the name of the invention that made printing easier?
What’s the difference between anaerobic exercise and aerobic exercise?
Cardelia is visiting the national aquarium in washington, d.c., and is watching the seahorses swim with various fish. she begins thinking about the human brain,
Why is important to be aware of behaviours of concern e.g aggression?
what is a compass and straightedge to construct a segment whose length is AB + CD ?
What is the correct definition of an archeologist?
What item or items may contribute to asthma?
Explain what a rodhocetus is
ALGEBRA 1, SEM. 2 ----------------------------- A cannonball is shot straight up into the air. The height of the cannonball at time t is represented by the func
Use the diagram to answer the question. What is A U B? A. [0,1,3,6,8] B. [2,4] C. [1, 2, 3, 4, 6, 8] D. [0, 1, 2, 3, 4, 6, 8]